MnDOT provides update on I-94 construction

(Editor’s Note: The following article was submitted by Wright County.)

The Minnesota Department of Transportation has provided an update to the I-94 project between Maple Grove and Clearwater that is scheduled to be completed later this year. The current focus of a lot of the work is the installation of concrete lanes and double boxes in the westbound lanes at Silver Creek.

Under the current schedule, there are some important dates coming up over the next two weeks. The ramp from Maple Grove Parkway to westbound I-94 is slated to reopen Monday, Aug. 30. The closure of westbound Territorial Road from Holly Lane in Dayton is scheduled to end Tuesday, Aug. 31. The ramp from westbound I-94 to Weaver Lake Road is scheduled to re-open Monday Sept. 6.