Minnesota Power and Great River Energy filed an application for a Certificate of Need and Route Permit from the Minnesota Public Utilities Commission (MPUC) to build a high-voltage transmission line to bolster electric reliability in northern and central Minnesota.
The Northland Reliability Project is an approximately 180-mile, double-circuit, 345-kilovolt (kV) transmission line, primarily following existing transmission corridors, from northern Minnesota to central Minnesota. It will help maintain a reliable and resilient regional power grid as more renewable energy is brought online, existing coal plants are transitioned, electrification continues to expand, and more frequent extreme weather events occur.
The jointly developed project is one of 18 transmission projects approved in July 2022 by the region’s grid operator, the Midcontinent Independent System Operator (MISO), in the first phase of its Long-Range Transmission Plan to integrate new generation resources and boost grid resilience as the energy transition continues. The Northland Reliability Project is the first project in this portfolio to reach this milestone of a state regulatory process.
The companies jointly held nearly 30 public open houses and numerous stakeholder meetings over the past year to provide opportunities for engagement with landowners, local governments, agencies, and Tribal Nations. This public feedback is reflected in the proposed route.
Subject to regulatory approvals, the companies expect construction to begin in 2027 and the line to be operational in 2030. Total cost is estimated between $970 million and $1.3 billion. The MPUC will determine need and the final route, and separately review cost recovery for Minnesota Power’s share of the project. MISO allocation will help offset costs for customers and members.
Utilities across the region are significantly increasing the amount of renewable energy they provide to their customers. By reducing coal-based energy and more than doubling renewable energy, Great River Energy anticipates that by 2035 its retail electric sales will be provided by a 90% carbon-free power supply in alignment with the Minnesota carbon-free standard. Minnesota Power was the first utility in the state to deliver 50% renewable energy to customers in 2021 with plans to be more than 70% renewable by 2030.
Project details
The Northland Reliability Project is divided into two segments.
Segment one: Approximately 140 miles of new 345-kV double-circuit transmission lines will be constructed primarily near existing transmission line corridors, from Minnesota Power’s Iron Range Substation in Itasca County to Great River Energy’s Benton County Substation near St. Cloud.
Segment two: A 20-mile 230-kV line will be replaced with two 345-kV circuits along existing transmission corridors from the Benton County Substation to a new Big Oaks Substation that will be built as part of a separate project. A 20-mile 345-kV line will also be replaced along existing transmission corridors from the Benton County Substation to the Sherco Substation in Sherburne County.
For more information and a map of the Northland Reliability Project’s route corridor, visit https://northlandreliabilityproject.com. People also can subscribe to receive updates about the project from the MPUC. Visit edockets.state.mn.us and enter docket 22-416 for information on the Certificate of Need or docket 22-415 for information on the Route Permit.