Public Notice

ADVERTISEMENT FOR BIDS

CP 71-673-019

Reconstruction of CR 73 from CSAH 11 to 

Elk River Bridge 

SHERBURNE COUNTY, MINNESOTA

NOTICE is hereby given that electronic bids will be accepted through the Sherburne County online bid portal https://bldvault.mn.uccs.com/ until 1:00 PM on Thursday, November 16, 2023 . This will be the only means of submittal of a bid. 

The Major Quantities of Work are: 

Clearing & Grubbing LS 

Bituminous Removal SY 49,580

Common Excavation/Embankment CY 112,260

Granular Borrow CY 2,200 

Aggregate Base and Shouldering TON 23,030

SP 9.5 & 12.5 Wearing Course Mixture TON 13,140 

15” -24” Storm Sewer Pipe / Culverts LF 570 

Seeding AC 18

Pavement Markings LF 39,900 

The bids will be reviewed by the County Engineer and County Attorney for the approval of the bid bond and the results of the review shall be posted within 3 business days at the following website: https://mn-co-sherburne.app.rtvision.com/oneoffice. Review of the bids by the County Engineer and the County Attorney should not be construed as an award of the bid. The final approval of the bid requires action by the County Board. 

Plans & specifications may be examined at the office of the Sherburne County Highway Engineer, 13880 Business Center Drive Suite 100, Elk River MN 55330, Monday-Friday 8 am to 4:30 pm, or online at https://www.co.sherburne.rnn.us/publicworks/index.php & follow the Construction Projects & Bids (eGram) link. A user ID & password is required to download the Plans & Specifications. Contact Public Works at 763-765-3300 to obtain the necessary information. 

The advertisement for this project may also be viewed at the MnDOT State Aid for Local Transportation eAdvert web site at https://eadvert.rtvision.com 

The cost to download the Plans & Specifications is free. 

The cost to obtain a hard copy of the Plans & Specifications is $50.00 with an additional $10.00 mailing fee. 

THE COST TO SUBMIT A BID WILL BE $25.00 PAYABLE TO RTVISION WHICH ALLOWS ACCESS TO THE ELECTRONIC BID DOCUMENTS VIA BID VAULT AT https://bidvault.mn.uccs.com. 

Ali bids shall be accompanied by a bid bond for at least five percent (5%) of the amount of the bid. 

No bidder may withdraw their bid (which shall include the bid bond) within 15 days of the scheduled bid submittal date of Thursday, November 16, 2023. 

The County Board reserves the right to reject any or all bids and to waive minor irregularities. The County Board will consider award of the contract at the December 7, 2023 County Board Meeting contingent upon County Engineer & County Attorney review. 

it is the County’s intent to have construction activities begin early February 2024 and be completed by the end of August 2024. 

The County Board reserves the right to reject any or all bids & waive informalities. 

Dated at Elk River Minnesota, this 17th day of October 2023. 

/s/  Bruce Messelt, County Administrator, Sherburne County, Minnesota

(Published in the Patriot: 10/21/23, 10/28/23, 11/04/23.)